You can migrate existing standard processes into visual processes.

To migrate a process

  1. On the Navigation Tree, click Automator and select Visual Processes.

  2. On the displayed page, select the Migrate Standard Processes tab.

  3. Select the process you want to export. Multiple selection is available.

  4. Enable the Change locations on import check box to substitute all locations values to the selected new location.

  5. Click the Migrate button. A message box will inform you that the migrate operation is complete.

Note: You can migrate only the processes with projects from the Server Library location.

If you exceed the number of processes allowed by your license, the following message appears: