Connectors and E-Line Management Tutorial
This section of the tutorial will walk you through the steps of review and realizing E-Lines.
Realizing E-Lines
-
Using standard Windows multi select option (Holding Ctrl key and selecting
Elines from the table), click Realize
Once all the lines are realized, you can view the message log for information.
-
Once the realization completes, you can see the status has changed from
Yellow to Green
-
Select any line from the list and click Visibility buttons at the top of the
table to view the lines.
The selected line will be isolated in graphics area.
- Click navigation buttons or beside Show Selected to cycle through other lines in the table.
Updating an E-Line
- Select DriverSidepanel_To_IPsubstrate from the list.
-
With the current line selection active, change Spacing
value to
50
and press Enter.This updates the spacing value from30
to50
and the line status changes to unrealized. You can see the new connector locations in the graphics area. -
Select DriverSidepanel_To_IPsubstrate from the list and
click Realize Selected.
This will re-realize the lines and
5
connectors will be realized for the interface.
Deleting Connection Point
- Select Ipsubstrate_To_Controlpanellower from the list and click Show Selected.
-
Click Delete Connection
.
This will enable Element Delete panel.
-
Select any CBUSH element from graphics area and click
proceed.
This will delete the selected CBUSH and respective RBE from the line and the same will be updated in Interface Number.
- Click Next to continue to Material Mapping task, which is the next step in process.