Plot the Value Against Time for an Abaqus ODB Result Type

  1. From the Build Plots panel, select the same result type and request for both the X and Y data.
  2. Select Time as the X Component.
  3. Select Value as the Y Component.
    The Value component is the actual value for the result type.
  4. Click Apply.